Posted by john newns apppreciate any help thank John
![]()
on 3/6/2005, 10:47 pm
Having conflict between building control and builders with advice on dpc.
I am up to lintel height with whole building ( block outer block inner skin with solid fill rockwool cavity 100mm ) I am about to place Catnic lintel but am unsure which way to fold the dpc runnin up closed cavities. I have a length of dpc at top of walls that has to be folded either to outskin or inner skin before lintel goes on top of it. Can anyone advise as to which way to fold the dpc. Inner skin would seem sensible but building dept says outer.